First concrete poured into turbine building foundation at Leningrad-2-3

AtomInfo.Ru, PUBLISHED 09.09.2026

Concreting of the turbine building foundation has begun at the Unit 3 (VVER-1200) of Leningrad NPP-2, reports the Rosenergoatom website.

At present, construction workers have filled the central section of the future foundation with nearly 5,000 cubic meters of concrete mix. This is the first stage of the structural works.

In total, the creation of the high-strength foundation will require nearly 5,000 tonnes of steel rebar and more than 20,000 cubic meters of high-strength concrete.

The work is being carried out in parallel across seven sections. As a result, specialists will create a monolithic slab 2.5 meters thick with an area of more than 8,000 square meters.

Topics: Leningrad NPP, Russia


Other news:

Construction of first NPP in Uzbekistan is launched

Ceremony marked pouring of first concrete.

Rosatom Enters Indian Market of Additive Manufacturing

RusBeam 2800 industrial 3D printer has successfully supplied.

Rosatom provides first nuclear fuel shipment to Xudapu NPP

Initial fuel loading for the VVER-1200 reactor at Unit 3.


Hero of the day

Welding of Primary Coolant Piping Completed at Akkuyu-2

Welding of Primary Coolant Piping Completed at Akkuyu-2

The welding was completed in 73 days - the time required to carry out welding operations on all 32 pipe joints.



INTERVIEW

Rosatom

Rosatom
On November 18, in St. Petersburg, President of Russia Vladimir Putin took part via videoconference in the keel-laying ceremony for the Project 22220 sixth serial-produced universal nuclear-powered icebreaker Stalingrad.


OPINION

CNNC

CNNC
On July 12, China National Nuclear Corporation (CNNC) achieved a milestone at the "National No 1 Uranium" demonstration project in Ordos, Inner Mongolia autonomous region, producing its first barrel of uranium product.


Search: