Forum   Contacts   RSS
AtomInfo.Ru


Construction of Akkuyu NPP Unit 3 Begins

Communications Department of ROSATOM, PUBLISHED 12.03.2021

A ceremony commemorating the start of Unit 3 construction was held at the site of the first Turkish nuclear power plant Akkuyu.

Russian President Vladimir Putin and Turkish President Recep Tayyip Erdogan joined the ceremony via videoconference. Energy and Natural Resources Minister Fatih Donmez, ROSATOM Director General Alexey Likhachev and Akkuyu Nuclear JSC CEO Anastasia Zoteeva were present at the Akkuyu NPP site.

At the ceremony, the leaders of the two countries gave permission to start construction work by pouring the first concrete into the foundation of Unit 3. Speaking at the event, Alexey Likhachev noted that construction work was progressing rapidly.

"Just three years after the Akkuyu NPP construction began, we are starting full-scale construction work on the third power unit. The project is proceeding at an unprecedented speed. I would like to express my sincere gratitude to the Turkish government and local officials for their comprehensive support of the project. Only through the support of the country's leadership, Turkish industrial companies and the public, we will be able to build the nuclear power plant quickly and efficiently. The NPP will be one of the cornerstones for the country's energy security," he said.

Fatih Donmez commented: "Construction and commissioning of the plant will provide 10% of Turkey's electricity needs. It is also important contribution to the preservation of our ecology: nuclear power plants are a source of environmentally friendly and uninterrupted electricity. The project is a driver for the development of industry, economy, employment, and also contributes to the development of many related industries."

The construction license for Unit 3 was issued by the Nuclear Regulatory Authority (NDK) on November 13, 2020. Concrete is being poured onto the reinforced base of the power unit. The foundation is divided into 16 work zones, so-called sections. Concrete pouring at each section will be carried out round the clock, and a technical shelter will protect the site from precipitation. Concrete will be poured to a height of 2.6 meters; the average volume of each section will be 1,100 cubic meters. The total amount of concrete mixture poured into the foundation slab as part of the concrete pouring works will be 17,000 cubic meters.

The whole set of preparatory works preceded the foundation slab concrete pouring: arrangement of water drawdown, excavation of the pit, arrangement of the concrete pad and waterproofing, foundation reinforcement and installation of embedded parts. Specialists are present on site to control the concrete pouring process, including experts from the concrete batching plant laboratory, representatives of AKKUYU NUCLEAR JSC, main construction contractor TITAN 2 IC ICTAS INSAAT ANONIM SIRKETI Joint Venture, as well as employees of the independent construction supervision organization Assystem EOS, a French engineering company.

Construction and installation works are now being carried out simultaneously at the construction sites of all four Akkuyu NPP power units. The concreting of the foundation slab of Akkuyu NPP Unit 1 was completed in March 2019. Up to this date, the core catcher, dry protection, the cantilever truss, and support and thrust trusses have been installed in the unit's reactor building. The work continues on concreting the walls of the internal structures of the containment, construction of structural contour walls and internal walls, pre-assembly and preparation for installation of the third tier of the inner containment shell.

The concreting of the foundation slab of Akkuyu NPP Unit 2 began on April 8, 2020 and was completed in early June 2020. Construction of the circular reactor building walls followed at the unit. Concrete pouring of the annular floor was carried out, the core catcher was installed in the design position, and the first tier of the internal containment shell was erected. Installation of the support truss in the design position is the next milestone planned for this year within the framework of the power unit construction.

The application documentation for the Akkuyu NPP Unit 4 construction license was submitted to NDK on May 12, 2020. Preparations are underway at the construction site for the construction of a foundation pit for the unit.

Topics: NPP Akkuyu, Asia, Turkey, Rosatom


Other news:

TVEL Elemash Machine-building plant launches new manufacturing site for CFR-600 fabrication

The dummy fuel bundles for CFR-600 are already manufactured for testing.

All spent fuel was unloading from SFP-3 at Fukushima Daiichi NPP

SFP-3 and SFP-4 are free of fuel now.

Rosatom will manufacture unique equipment for the BREST-OD-300 power unit

Installation of the main equipment should be completed in 2025.

Hero of the day

Nuclear fuel elements for Chinese HTGR shipped

Nuclear fuel elements for Chinese HTGR shipped

The shipment of 78,000 spherical fuel elements to the demonstration plant is part of an initial delivery of 870,000 spherical fuel elements, which are expected to be put into the reactor in April.



INTERVIEW

Vladimir Kriventsev

Vladimir Kriventsev
The International Atomic Energy Agency brings together the fast reactor and related fuel cycle community and countries and the wider public interested in these technologies by organising the International Conference on Fast Reactors and Related Fuel Cycles: Sustainable Clean Energy for the Future or FR21.


OPINION

Victor Murogov

Victor Murogov
This critical analysis of the history, state, and prospects of development of modern nuclear technologies shows that nuclear energy market has practically monopolized the design and construction of only one type of reactors (95% of NPPs under construction use pressurized water reactors), which necessitates training of focused specialists involved in the construction and operation of those nuclear power plants.


Search: