The welding of the main circulation pipeline has been completed ahead of schedule at the Tianwan Nuclear Power Plant Unit 8

Atommedia, PUBLISHED 12.09.2025

At Unit 8 of the Tianwan NPP, which is being built with Rosatom's support in China, a crucial construction milestone has been completed ahead of schedule: the welding of the main circulation pipeline (MCP).

The MCP connects the components of the reactor plant - the reactor vessel, steam generators, and main circulation pumps.

Simultaneously, at the adjacent Tianwan NPP Unit 7, the cold and hot functional testing phase of the reactor plant has begun. This process marks the transition to full-scale commissioning.

Topics: Asia, China, NPP Tianwan


Other news:

CIAE makes breakthrough in key technologies for integral fast reactor

CIAE has successfully completed the principle verification test of the integral residual heat removal system.

IAEA issues technical document on tritium in environment

The document has 362 pages and 93 illustrations.

416 nuclear units are operating in the world

62 units are under construction.


Hero of the day

Rosatom completed manufacturing the second RITM-400

Rosatom completed manufacturing the second RITM-400

In total, taking into account the two giant reactors, we have manufactured 12 RITM series reactor units. Another 14 are in the works for the nuclear icebreaker fleet and SMR projects.



INTERVIEW

Rosatom

Rosatom
Representatives of Rosatom State Corporation took part in the World Nuclear Association (WNA) Symposium, which ended on September 5 in London, United Kingdom.


OPINION

CNNC

CNNC
On July 12, China National Nuclear Corporation (CNNC) achieved a milestone at the "National No 1 Uranium" demonstration project in Ordos, Inner Mongolia autonomous region, producing its first barrel of uranium product.


Search: