![]() |
||
|
NPP Akkuyu Polar crane installed at Akkuyu NPP Unit 2 Key component of the reactor cavity installed at Akkuyu NPP Unit 4 Head of Rosatom and Energy Minister of Turkiye held a working meeting at the Akkuyu NPP site Turbine Generator Stator Installed at Akkuyu NPP Unit 2 Reactor vessel for Unit 4 delivered to Akkuyu NPP site Key Component of Unit 4 Equipment Delivered to Akkuyu NPP Key Component of Unit 4 Equipment Delivered to Akkuyu NPP Rosatom started the final assembly of the reactor for unit 4 of the Akkuyu NPP Pump motors of service water supply system started up at Akkuyu NPP Unit 1 onshore pump station
One-hundredth cargo ship arrived at Akkuyu NPP cargo terminal Equipment start-up and adjustment started at the pumping station of Akkuyu NPP Unit 1 Siemens will be sued for refusing to supply paid equipment to Akkuyu-1 - Likhachev
The MCP electric motors are mounted on the first unit of the Akkuyu NPP Turbine building roof installation was completed at Akkuyu NPP Unit two Transportation airlock installed at Akkuyu NPP Unit No. 1 Clean area for controlled reactor assembly arranged at Akkuyu NPP Unit 1 Commissioning of the first unit of the Akkuyu NPP is scheduled for July 2025 The first full-scale NPP simulator was put into operation at the Akkuyu NPP in Turkey Rosatom had delivered the reactor pressure vessel for the Akkuyu NPP Unit 3 (Turkey) Rosatom commissions polar crane at Akkuyu NPP power unit No. 1 Core catcher is installed on the Akkuyu-4 Bridge crane of the turbine hall commissioned on the Akkuyu-1 unit Concreting of internal containment dome completed at Akkuyu NPP Unit No.1
Installation of the fourth tier of the containment at Akkuyu NPP Unit 2 is completed Turbine building roof installation completed at Akkuyu NPP Unit 1 Akkuyu NPP project employees collect help for earthquake victims Akkuyu Nuclear holds Open Doors Day at the NPP Construction site Next stage of containment installation was completed at Akkuyu-3 ROSATOM ships nuclear fuel mock-ups for testing the first unit of Akkuyu NPP in Turkey The Firefighters of AKKUYU NUCLEAR JSC were Awarded for Their Professionalism The most crucial assembly operation of the year started at Akkuyu NPP Unit 1 Turbine generator for Unit 1 delivered to Akkuyu NPP site License has been issued for the construction of Akkuyu-4 Nuclear News Ticker - June 02, 2021 AAEM LLC delivers its first rotor for Arabelle steam turbine to Akkuyu NPP site 444 nuclear units are operating in the world, 50 units are under construction
Nuclear News Ticker - March 12, 2021 Nuclear News Ticker - February 10, 2021 Nuclear News Ticker - December 15, 2020 Nuclear News Ticker - December 06, 2020 Nuclear News Ticker - December 01, 2020 Akkuyu Nuclear JSC Obtains the Construction License of Akkuyu NPP Unit 3 Nuclear News Ticker - November 18, 2020 Nuclear News Ticker - November 15, 2020 |
Hero of the day
Rosatom supplies the initial load of nuclear fuel for Tianwan-7 The nuclear fuel, including the initial core load and a number of fuel assemblies supplied as reserve, was manufactured at the Novosibirsk Chemical Concentrates Plant (an enterprise of Rosatom's Fuel Division). INTERVIEW
Rosatom OPINION
CNNC |